TOPOGRAPHICAL SURVEY FOR KIGOMA 400/220KV SUBSTATION
- Category: Project
- Published: Friday, 20 June 2025 08:58
- Written by Recafi
- Hits: 38
The topographical survey conducted for the Proposed Kigoma New Substation area in the Kigoma Region, Tanzania. The project scope encompasses the Design, Supply, Installation, Testing, and Commissioning of the New 400/132/33kV Kigoma (Kidahwe) Substation, along with the Extension of the 400/200kV Nyakanazi Substation. RECAFI Investment Company Limited (RECAFICO) was subcontracted to perform the topographical survey necessary for implementing this project.
The survey team from RECAFI was led by Licensed Surveyor Lwijiso Ngulwa, supported by Surveyor Hassan Ismail and assistant surveyor Jairiso Ulema. The topographical survey aimed to assess the terrain of the project site, identifying key features such as points, lines, and polygons crucial for the design and execution phases. This involved gathering data on spot heights and conducting detailed surveys
.